Nhan Co Alumina Refinery Project in Vietnam
×
Location:
Vietnam
Capacity:
650kt/a
Year of Completion:
2017
Mode:
EPC
Lam Dong Alumina Refinery Project in Vietnam
×
Location:
Vietnam
Capacity:
650kt/a
Year of Completion:
2013
Mode:
EPC
ETI Aluminum Smelter Modernization in Turkey
×
Location:
Turkey
Amperage:
300kA
Capacity:
77.8kt/a
Year of Completion:
2016
Mode:
E+P+Service
Bauxite Mine, Alumina and Aluminum Project
×
Location:
Laos
Capacity:
1,500kt/a Bauxite Mine
500kt/a Alumina Refinery
250kt/a Aluminum Smelter
Status:
To Be Completed
Mode:
Bankable Feasibility Study
SCPC Coke Calcination Plant Project (CPC Plant)
×
Location:
Saudi Arabia
Capacity:
670kt/a
Status:
Under Engineering
Mode:
EPC
Sarawak Aluminum Smelter Upgrading Project
×
Location:
Malaysia
Amperage:
215kA
Capacity:
110kt/a
Year of Completion:
2014
Mode:
Upgrading Engineering
Press Metal Bintulu Smelter in Malaysia
×
Location:
Malaysia
Amperage:
400kA
Capacity:
320kt/a
Year of Completion:
2015
Mode:
EP
CVG Venalum Modernization Project
×
Location:
Venezuela
Amperage:
160kA
Capacity:
448kt/a
Status:
Under Construction
Mode:
EPC
ALCASA Aluminum Smelter Modernization Project
×
Location:
Venezuela
Amperage:
160kA
Capacity:
170kt/a
Year of Completion:
2015
Mode:
EPC
Alumina Refinery Project in Guinea
×
Location:
Guinea
Capacity:
1,000kt/a
Year of Completion:
2020
Mode:
Bankable Feasibility Study
ITER Poloidal Field (PF) AC/DC Converter System
×
Location:
France
Status:
Under Installation
Mode:
Engineering + Installation Supervision
Revamping PortoVesme Smelter in Italy
×
Location:
Italy
Amperage:
increased from 165kA to 180kA
Capacity:
155.8kt/a
Status:
Under Engineering
Mode:
E+P+Service
Jajarm Alumina Refinery Modification in Iran
×
Location:
Iran
Capacity:
280kt/a
Year of Completion:
2003
Mode:
Upgrading Engineering
Coke Plant of James Durrans & Sons Ltd
×
Location:
South Africa
Capacity:
12kt/a
Year of Completion:
2018
Mode:
EP
Pot Upgrading for Higher Amperage of Inalum
×
Location:
Indonesia
Amperage:
increased from 195kA to 235kA
Year of Completion:
2017
Mode:
EPC
Mempawah Smelter Grade Alumina Refinery Project
×
Location:
Indonesia
Capacity:
1,000kt/a
Status:
Under Engineering
Mode:
EPC
LAMAN Alumina Refinery Project
×
Location:
Indonesia
Capacity:
2,000kt/a
Year of Completion:
2020
Mode:
FEED
Aluminum Smelter in Ecuador
×
Location:
Ecuador
Amperage:
500kA
Capacity:
560kt/a
Year of Completion:
2016
Mode:
Bankable Feasibility Study